@ „ TOP „  1 „  2 „  3 „  4 „  5 „  6 „  7 „  9 „  10 „  11 „  12 „  13 „  14 „  15 „  16 „  17 „  18 b

Assignment Name:
Emergency Electric Power Improvement Project for Thermal Power Plant Kakanj

Country: Bosnia and Herzegovina

Client: "Elektroprivreda" Bosnia and Herzegovina (EPBiH)

Financial Source: Japan Bank of International Cooperation (JBIC), and EPBiH own fund

Service Period: August 2001 to February 2006

Narrative Description of Project:

The objective of the rehabilitation and improvement of Thermal Power Plant "Kakanj" is to:

  • Improve reliability of Unit 5,
  • Improve reliability of the water treatment/cooling water plant as common facilities,
  • Improve performance and reliability of Unit 7, and
  • Mitigate environmental impact by reducing emission of dust and NOx from Unit 7

This project is financed by JBIC ODA Loan covers this project and four coal mines, as a part of the larger project co-financed by JBIC and the World Bank which aims to rehabilitate four thermal power plants, four coal mines, five hydroelectric plants and transmission and distribution lines.

Services :
  • Preparation of rehabilitation plan
  • Preparation of tender documents
  • Assistance in bidding
  • Bid evaluation
  • Check and review of manufacturesf design and drawings
  • Assistance in the inspection and witness to shop tests
  • Construction supervision
  • Assistance in commissioning
  • Study on environmental improvement
  • Recommendation of optimum coal mixture